Tel: +86-371-65621392 | Email: info@haomei.biz

The proper switching process of concrete mixing plant

Writer:Admin   Time:17/06/15

     The open and shut down of the concrete mixing plant is a very simple operation for many people. Can you do the right switch concrete mixing plant? This correct operation will undoubtedly affect your machine life and long-term normal operation.


    Concrete mixing plant correct start process: the first choice to open the water valve switch to the pump water, followed by air compressor open storage warehouse door, and then open the discharge belt, open the mixing host, feeding belt machine and batching machine, and finally open the water switch .
    Concrete mixing plant correct shutdown process: first off the dosing machine, water supply switch, feeding switch (to ensure that no material on the hopper) followed by closing the mixing console, unloading belt switch machine storage door and air compressor off. Finally, clean the mixing cylinder to turn off the water switch switch level of the total power of the switch can be.